STATE |
WIRE CENTER |
PLANNED COMPLETION OR RETIREMENT DATE |
DA (s) |
Job # |
FDI Address(es) |
Replacing |
AZ
|
Tucson North TCSNAZNO
|
05-15-2012
|
213511
|
E.296032
|
270 E Orange Grove Rd
|
Road construction forces CenturyLink to abandon its copper cables and transfer working services to a fiber fed digital loop carrier system (DLC). Copper reliant services, such as non-loaded copper loops and line sharing will no longer be supported after the cut to DLC; all other types of unbundled loops will still be available.
|
AZ
|
Tucson North TCSNAZNO
|
05-15-2012
|
213412, 213412
|
E. 295952, E.295952
|
F 505 W Orange Grove Rd
|
Road construction forces CenturyLink to abandon its copper cables and transfer working services to a fiber fed digital loop carrier system (DLC). All existing services will continue to be supported; however, after the cut to DLC, new copper reliant services, such as non-loaded copper loops will not be supported. All other types of unbundled loops will still be available.
|
AZ
|
Tucson North TCSNAZNO
|
05-15-2012
|
210412
|
E.291893
|
7400 N Oracle Rd
|
Road construction forces CenturyLink to abandon its copper cables and transfer working services to a fiber fed digital loop carrier system (DLC). Copper reliant services, such as non-loaded copper loops and line sharing will no longer be supported once the facilities are cut over to DLC; all other types of unbundled loops will still be available.
|
AZ
|
Tucson North TCSNAZNO
|
05-15-2012
|
213014
|
E.291976
|
7250 N Oracle Rd
|
Road construction forces CenturyLink to abandon its copper cables and transfer working services to a fiber fed digital loop carrier system (DLC). Copper reliant services, such as non-loaded copper loops and line sharing will no longer be supported once the facilities are cut over to DLC; all other types of unbundled loops will still be available.
|
AZ
|
Tucson North TCSNAZNO
|
05-15-2012
|
213213, 213211, 213212
|
E.292600
|
6550 N Oracle Rd
6508 N Oracle Rd
6499 N Oracle Rd
|
Road construction forces CenturyLink to abandon its copper cables and transfer working services to a fiber fed digital loop carrier system (DLC). Copper reliant services, such as non-loaded copper loops and line sharing will no longer be supported once the facilities are cut over to DLC; all other types of unbundled loops will still be available.
|
AZ
|
Tucson North TCSNAZNO
|
05-15-2012
|
213111
|
E.292536
|
6800 N Oracle Rd
6970 N Oracle Rd
|
Road construction forces CenturyLink to abandon its copper cables and transfer working services to a fiber fed digital loop carrier system (DLC). All existing services will continue to be supported; however, after the cut to DLC, new copper reliant services, such as non-loaded copper loops will not be supported. All other types of unbundled loops will still be available.
|
AZ
|
Tucson North TCSNAZNO
|
05-15-2012
|
213413, 213411, 213413, 213211
|
E.294079
|
101 W Orange Grove Rd
6200 N Oracle Rd
6251 N Oracle Rd
401 W Orange Grove Rd
6199 N Oracle Rd
6281 N Oracle Rd
6261 N Oracle Rd
6363 N Oracle Rd
6400 N Oracle Rd
6380 N Oracle Rd
6350 N Oracle Rd
6390 N Oracle Rd
|
Road construction forces CenturyLink to abandon its copper cables and transfer working services to a fiber fed digital loop carrier system (DLC). Copper reliant services, such as non-loaded copper loops and line sharing will no longer be supported once the facilities are cut over to DLC; all other types of unbundled loops will still be available.
|
AZ
|
Tucson North TCSNAZNO
|
05-15-2012
|
211111, 212011, 211711, 211712
|
E.296185
|
1000 E Ina Rd
1805 E Chula Vista Rd
2002 E Skyline Dr
1701 E Ina Rd
2333 E Ina Rd
|
Road construction forces CenturyLink to abandon its copper cables and transfer working services to a fiber fed digital loop carrier system (DLC). Copper reliant services, such as non-loaded copper loops and line sharing will no longer be supported once the facilities are cut over to DLC; all other types of unbundled loops will still be available.
|
AZ
|
Tucson North TCSNAZNO
|
06-15-2012
|
213414
|
E.294457
|
6053 N Oracle Dr
6181 N Oracle Dr
|
Road construction forces CenturyLink to abandon its copper cables and transfer working services to a fiber fed digital loop carrier system (DLC). Copper reliant services, such as non-loaded copper loops and line sharing will no longer be supported once the facilities are cut over to DLC; all other types of unbundled loops will still be available.
|
AZ
|
Beardsley BRDSAZMA
|
06-01-2012
|
310612
|
E.295963
|
17151 N Parkview Pl
|
Road construction forces CenturyLink to abandon its copper cables and transfer working services to a fiber fed digital loop carrier system (DLC). Copper reliant services, such as non-loaded copper loops and line sharing will no longer be supported once the facilities are cut over to DLC; all other types of unbundled loops will still be available.
|
IA
|
Waterloo
|
04-01-2012
|
240503, 240502
|
E.291982
|
3100 Logan
2637 Logan
|
Road construction forces CenturyLink to abandon its copper cables and transfer working services to a fiber fed digital loop carrier system (DLC). Copper reliant services, such as non-loaded copper loops and line sharing will no longer be supported once the facilities are cut over to DLC; all other types of unbundled loops will still be available.
|
IA
|
Waterloo WTRLIADT
|
04-01-2012
|
240402
|
E. 292185
|
1517 Wakonda
|
Road construction forces CenturyLink to abandon its copper cables and transfer working services to a fiber fed digital loop carrier system (DLC). All existing services will continue to be supported; however, after the cut to DLC, new copper reliant services, such as non-loaded copper loops will not be supported. All other types of unbundled loops will still be available.
|
IA
|
Waterloo WTRLIADT
|
04-01-2012
|
230203
|
E. 292154
|
502 Keystone
|
Road construction forces CenturyLink to abandon its copper cables and transfer working services to a fiber fed digital loop carrier system (DLC). All existing services will continue to be supported; however, after the cut to DLC, new copper reliant services, such as non-loaded copper loops will not be supported. All other types of unbundled loops will still be available.
|
MN
|
Coon Rapids CNRPMNND
|
03-15-2012
|
280101
|
E. 509461
|
12528 University Ave NW
|
Road construction forces CenturyLink to abandon its copper cables and transfer working services to a fiber fed digital loop carrier system (DLC). All existing services will continue to be supported; however, after the cut to DLC, new copper reliant services, such as non-loaded copper loops will not be supported. All other types of unbundled loops will still be available.
|
MN
|
Rochester ROCHMNRO
|
05-12-2012
|
320803
|
E.540988
|
Pinewood Rd and 23 St SE
|
Road construction forces CenturyLink to abandon its copper cables and transfer working services to a fiber fed digital loop carrier system (DLC). All existing services will continue to be supported; however, after the cut to DLC, new copper reliant services, such as non-loaded copper loops will not be supported. All other types of unbundled loops will still be available.
|
MN
|
Rochester ROCHMNRO
|
05-11-2012
|
320802, 320804
|
E.545527
|
Pinewood Rd SE
2701 Simpson Rd SE
|
Road construction forces CenturyLink to abandon its copper cables and transfer working services to a fiber fed digital loop carrier system (DLC). All existing services will continue to be supported; however, after the cut to DLC, new copper reliant services, such as non-loaded copper loops will not be supported. All other types of unbundled loops will still be available.
|
NE
|
Fowler OMAHNEFW
|
05-11-2012
|
115302
|
E.545466
|
13000 N River Dr
|
Road construction forces CenturyLink to abandon its copper cables and transfer working services to a fiber fed digital loop carrier system (DLC). All existing services will continue to be supported; however, after the cut to DLC, new copper reliant services, such as non-loaded copper loops will not be supported. All other types of unbundled loops will still be available.
|
WA
|
Maple Valley MPVYWAMV
|
05-30-2012
|
312301, 312701, 312801
|
E.295279
|
23605 Se 244th
24390 St Se
25104 Maple Valley
|
Road construction forces CenturyLink to abandon its copper cables and transfer working services to a fiber fed digital loop carrier system (DLC). All existing services will continue to be supported; however, after the cut to DLC, new copper reliant services, such as non-loaded copper loops will not be supported. All other types of unbundled loops will still be available.
|
WY
|
Casper CSPRWYMA
|
06-30-2012
|
215932
|
E.545462
|
798 Iron
|
Due to landslide, CenturyLink is forced to re-route its facilities and is moving working services to a fiber fed digital loop carrier system (DLC). Copper reliant services, such as non-loaded copper loops and line sharing will no longer be supported after the cut to DLC; all other types of unbundled loops will still be available.
|